Incident Reports
4/5/2024
Tavas Lattimer
Director of Systems Administration
As many of you probably know, we had a data center move scheduled for April 1st (no, this wasn’t meant to be an April Fools joke). Unfortunately, our move didn’t go as we would’ve liked it to.
To get you up to speed (if you don’t know this already, which most people don’t), here’s a little bit about how we ended up with the locations we have. When Xentain opened, we started with VPS hosting in Vancouver. After the high demand for Vancouver and other locations, we decided to start offering virtual private servers in Fremont, California. Once Fremont had sold out after several restocks, we decided it was time to open a US Central location in Dallas, Texas. We ended up getting a cabinet with Flexential in their RCH01 location. One of the main reasons we chose the RCH01 location is because our remote hands technician was close by.
Flexential’s RCH01 data center was a nice data center, and was working well for us, until we had to upgrade to a 10 Gbps connection (we outgrew our 1 Gbps connection quickly). For some reason Cogent, our current carrier in Dallas, wouldn’t properly bill us for a 1 Gbps line (Xentain is a Canadian company in American data centers, and apparently its too hard to bill us in CAD instead of USD). To replace Cogent, we planned to use Hurricane Electric, as we have been happy with their services in the past (and we really like Cat5 the ColoCat!) This is where the issues start. After looking at the carriers in Flexential’s RCH01 data center, we realized that Hurricane Electric wasn’t listed. HE is in most data centers, but apparently they weren’t in RCH01. The only way we were going to be able to get a connection to HE while in RCH01 was going to be getting a cross connect from RCH01 to Flexential’s DAL02 (DAL01? They both have the same suite and address on PeeringDB), Flexential’s suite in Equinix’s Infomart in Downtown Dallas.
We ended up deciding it would be easier to just move data centers entirely, as we would have more opportunities to get other carriers in DAL02 if Hurricane Electric didn’t end up working out for us in the long run. We scheduled our data center move for April 1st, 2024, a few weeks after getting our new cabinet in DAL02.
April 1st came faster than we anticipated. We had scheduled a maintenance from 6am on April 1st to 12am on April 2nd. Unfortunately, we ended up having to extend the window to 12am on April 3rd. A timeline of the move has been provided below.Timeline
All times provided below are in Eastern Time. Times have also been approximated from the actual times things happened.
April 1st:
April 2nd:
April 4th:
To summarize: The data center move started and ended later than we had hoped for and Hurricane Electric’s optic ended up having issues, and a bunch of stuff on our end wasn’t configured properly (including switch ports). A few days later, a technician went to the data center to install a 10 Gbps network interface into our router so we could try to do 10 Gbps, but apparently, our optic didn’t want to work, so a new one was ordered.
I owe a big thank you to everyone at Flexential and Hurricane Electric who worked with us as we tried to troubleshoot these issues. I also owe a very big thank you to our remote hands technician, Joseph, for being patient with us while we tried to restore everything.